Market briefs · Europe
Data centres in Europe 2026: where capacity and hiring are moving
By the Workfully data centre hiring team · Last reviewed
Summary
Data centres in Europe are growing fastest away from the five hub cities. Greenfield sites make up 39% of Europe's 2026–2028 pipeline, against 8% of recent deliveries (JLL, Aug 2026). For hiring teams, that means campuses in places with few experienced electrical and mechanical people, in a labour market already short of electricians.
Key facts
- EMEA operational data centre capacity passed 12.1 GW in the first half of 2026, with a committed pipeline of 18.3 GW: 3.8 GW under construction and 14.5 GW planned. (Cushman & Wakefield, 14 September 2026)
- The five core markets hold 43% of EMEA operational capacity but only 32% of the future pipeline, down from 39% six months earlier. (Cushman & Wakefield, 14 September 2026)
- Hyperscale campuses planned for 2026 to 2028 sit an average of 175 km from a hub city, against 46 km for projects delivered between 2022 and 2025. (JLL, 6 August 2026)
- The EU's proposed Cloud and AI Development Act, published in June 2026, aims to triple EU data centre capacity within five to seven years. (Council of the European Union, 4 June 2026)
- In the 2025 EURES labour shortages report, 21 European countries report a shortage of building and related electricians. (European Labour Authority, June 2026)
Data centre (data center in US usage) building in Europe is moving out of the hub cities and towards wherever power can be delivered. Hyperscale campuses planned for 2026 to 2028 sit an average of 175 km from a hub city, against 46 km for those delivered in 2022 to 2025 (JLL, Aug 2026). That changes who a project can hire locally, and how many senior people it must move to site.
How much data centre capacity is Europe building in 2026?
Across EMEA (Europe, the Middle East and Africa, so Europe's own total is lower), operational capacity passed 12.1 GW in the first half of 2026, up more than 36% in two years (Cushman & Wakefield, Sep 2026). The committed pipeline reached 18.3 GW, with 3.8 GW under construction and 14.5 GW planned (Cushman & Wakefield, Sep 2026).
London remains the largest single market, with 1.38 GW operational (Cushman & Wakefield, Sep 2026). Paris has overtaken Dublin as the third-largest market by total capacity. Cushman & Wakefield sees little sign of oversupply, with vacancy under 10% across most operational sites (Cushman & Wakefield, Sep 2026).
JLL measures the five hub cities separately. Frankfurt, London, Amsterdam, Paris and Dublin have about 3.8 GW live, 1.4 GW under construction and 2 GW planned (JLL, Aug 2026). Colocation vacancy across the five stood at 6.4% in the second quarter of 2026, with Frankfurt tightest at 3.1% (JLL, Aug 2026).
Where is new capacity going?
Away from the core. The five hub markets hold 43% of EMEA operational capacity but only 32% of the future pipeline, down from 39% six months earlier (Cushman & Wakefield, Sep 2026). Greenfield sites account for 39% of Europe's future pipeline, compared with 8% of projects delivered in the previous three years (JLL, Aug 2026).
Power is the reason. Cushman & Wakefield says power availability, permitting and grid capacity increasingly decide where new data centres can be built (Cushman & Wakefield, Sep 2026). In the hub cities, JLL reports lead times of up to 10 years for workloads that must sit close to users (JLL, Aug 2026).
Investment is accelerating fastest in selected Southern European and Scandinavian markets, according to Cushman & Wakefield. It names Madrid, Oslo, Warsaw, Vienna and Barcelona among markets still expanding, and Helsinki has joined its top tier with total capacity above 1.1 GW (Cushman & Wakefield, Sep 2026).
What is the EU doing to speed up data centre building?
The EU's Cloud and AI Development Act was proposed on 3 June 2026 (Council of the EU, Jun 2026). The proposal aims to triple EU data centre capacity in the next five to seven years (Council of the EU, Jun 2026). A second objective is that by 2030 operators can get every permit for a data centre, including land, energy and connectivity, in under 18 months (Council of the EU, Jun 2026). The proposal's objectives section states the capacity aim as at least tripling current capacity by 2030 (Council of the EU, Jun 2026).
The text also asks member states to set clear procedures for grid connection and flexible connection agreements. It is still a proposal before the Council and Parliament, so dates and thresholds may change. If it passes in this form, faster permits would likely pull hiring dates forward on sites that are now waiting.
Which trades are short across European markets?
Electrical trades top the list. In the 2025 EURES report, 21 countries report a shortage of building and related electricians, and only Greece and Finland report a surplus (European Labour Authority, Jun 2026). Electrical engineers are short in 16 countries, electrical mechanics and fitters in 17, and air conditioning and refrigeration mechanics in 16 (European Labour Authority, Jun 2026).
Construction surveys point the same way. In Turner & Townsend's 2026 index, 81% of respondents worldwide say skilled labour in their region is constrained, with MEP trades the most sought-after (Turner & Townsend, Oct 2026). EURES adds that 98% of occupations short in at least one country are in surplus in another (EURES, Jun 2026), which is the case for sourcing across borders.
Market tier and trade shortages by country
The table sets Cushman & Wakefield's market tiers against the data centre trades each country lists as in shortage or surplus in the EURES report. Tiers come from the Cushman & Wakefield H1 2026 update and trades from Table 21 of the EURES report, which covers EU and EEA countries.
| Country | Markets and tier (Cushman & Wakefield) | Trades reported in shortage (EURES 2025) | Trades reported in surplus |
|---|---|---|---|
| Germany | Frankfurt (primary), Berlin (secondary) | Electricians, electrical engineers, electrical fitters, HVAC mechanics, line installers | None of these |
| France | Paris (primary), Marseille (secondary) | Electrical fitters, HVAC mechanics | None of these |
| Netherlands | Amsterdam (primary) | Electricians, electrical engineers, electrical fitters, HVAC mechanics, line installers | None of these |
| Ireland | Dublin (primary) | Electricians, electrical engineers | None of these |
| Italy | Milan (primary) | Electricians, electrical engineers, electrical fitters, HVAC mechanics, line installers | None of these |
| Finland | Helsinki (primary) | Electrical engineers | Electricians, electrical engineers, electrical fitters, HVAC mechanics, line installers |
| Spain | Madrid, Barcelona, Zaragoza (secondary) | Line installers | None of these |
| Portugal | Lisbon (secondary) | Electricians, electrical engineers, electrical fitters, HVAC mechanics, line installers | None of these |
| Norway | Oslo (secondary) | Electricians, electrical fitters, line installers | None of these |
| Sweden | Stockholm (secondary) | Electricians, electrical engineers, electrical fitters | None of these |
| Denmark | Copenhagen (secondary) | Electricians, electrical engineers | None of these |
| Poland | Warsaw (secondary) | Electricians, electrical fitters, HVAC mechanics, line installers | None of these |
Electricians means building and related electricians; HVAC mechanics means air conditioning and refrigeration mechanics. Finland lists electrical engineers in both columns. A trade missing from a row is not reported as short or in surplus by that country; it does not mean supply is easy.
What does this mean for hiring teams?
A greenfield campus an average of 175 km from a hub city (JLL, Aug 2026) is likely to have few experienced data centre people living nearby. Senior construction, electrical and commissioning leads will often need to relocate or rotate to site, while a local operations team is recruited and trained.
The shortage lists also limit the usual fix of hiring from the next country. Electricians are short in most of the countries that report. Cross-border sourcing works best where the table shows a surplus, as in Finland, or where a country lists a trade in neither column.
Checklist for staffing a greenfield European site:
- Confirm the grid connection date with the network operator before opening senior searches.
- Map each role to its phase: enabling works, construction, commissioning or operations.
- Decide which leads must live near the site and which can rotate.
- Check which nearby projects, including grid and renewables work, compete for the same electricians and fitters.
- Use the shortage and surplus lists to choose the countries to source each trade from.
- Hire the future site manager before handover, so they learn the plant during commissioning.
- Plan a local training route for the permanent operations team from the start.
For country detail, see the briefs on Nordic data centre capacity and grid queues, Frankfurt and Germany, Spain and Portugal, Ireland, the Netherlands and the UK market. For headcount by phase, see how many people a data centre needs.
Planning a site far from the usual talent hubs? Workfully is an AI-native recruiting partner built around your hiring needs. Senior specialist recruiters deliver the hires your business needs without scaling your recruiting team. Your team interviews and decides (Workfully for data centres).
Frequently asked questions
- How much data centre capacity is there in Europe?
- Cushman & Wakefield puts EMEA operational capacity above 12.1 GW in the first half of 2026, up more than 36% in two years (Cushman & Wakefield, Sep 2026). Frankfurt, London, Amsterdam, Paris and Dublin together have about 3.8 GW live by JLL's count (JLL, Aug 2026). The two advisers count differently, so compare each with its own earlier editions rather than with each other.
- Which European data centre markets are growing fastest?
- Cushman & Wakefield says investment is accelerating fastest in selected Southern European and Scandinavian markets, and names Madrid, Oslo, Warsaw, Vienna and Barcelona among those still expanding (Cushman & Wakefield, Sep 2026). Helsinki has moved into its top tier with total capacity above 1.1 GW (Cushman & Wakefield, Sep 2026). Paris delivered 72.5 MW in the first half of 2026, ahead of its full-year forecast (JLL, Aug 2026).
- Is there a shortage of electricians in Europe?
- Yes, in most countries that report. The 2025 EURES report lists 21 countries with a shortage of building and related electricians, and only Greece and Finland with a surplus (European Labour Authority, Jun 2026). Data centre builds compete for the same people as grid, renewables and building retrofit work, which EURES names as drivers of demand for electricians (EURES, Jun 2026).
- What is the EU Cloud and AI Development Act?
- It is a proposed EU regulation, published on 3 June 2026 as COM(2026) 502 (Council of the EU, Jun 2026). It aims to triple EU data centre capacity in five to seven years. By 2030, operators should be able to obtain every permit for a data centre in under 18 months (Council of the EU, Jun 2026). It is a proposal, so its final terms depend on the Council and Parliament.
Related articles
Market briefs
Data centres in Norway and the Nordics: capacity, power, site teams
Norway paused new data centre grid reservations in Nov 2026. A Nordic brief on capacity, grid queues in four countries and what they mean for site hiring.
Last reviewed
Market briefs
Data centres in Germany: Frankfurt, Berlin, grid queues and hiring
Frankfurt data centre vacancy fell to 3.1% in 2026 and grid capacity for new requests is quoted from the mid-2030s. A German brief on capacity, power and staff.
Last reviewed
Market briefs
Data centres in Spain and Portugal: Madrid, Aragón, Lisbon, Sines
Iberia added 65 MW IT of live data centre capacity in six months to September 2026. A brief on Madrid, Aragón, Lisbon, Sines, grid access and site hiring.
Last reviewed
Market briefs
Data centres in the Netherlands: Amsterdam, Eemshaven and hiring
Amsterdam has 927 MW of data centre capacity and Dutch policy steers hyperscale to Eemshaven and Middenmeer. A Dutch brief on capacity, grid limits and staff.
Last reviewed
Sources
- Cushman & Wakefield. H1 2026 EMEA Data Centre Market Update. Published . Accessed . Tier B, research and press.
- Cushman & Wakefield. European Data Centre capacity surpasses 12GW. Published . Accessed . Tier B, research and press.
- JLL. AI boom redraws Europe's data centre map as power access overtakes location. Published . Accessed . Tier B, research and press.
- JLL. EMEA data centre mid-year 2026 report. Published . Accessed . Tier B, research and press.
- Council of the European Union. Proposal for a Regulation establishing a framework of measures for strengthening Europe's cloud and AI ecosystem (Cloud and AI Development Act), COM(2026) 502 final. Published . Accessed . Tier A, primary.
- European Labour Authority. EURES Report on labour shortages and surpluses 2025, Annex: Transnational matching possibilities (Table 21). Published . Accessed . Tier A, primary.
- EURES. What the latest data reveals about labour market imbalances across Europe. Published . Accessed . Tier A, primary.
- Turner & Townsend. Data centre construction cost index 2026-27. Published . Accessed . Tier B, research and press.