Market briefs · Germany

Data centres in Germany: Frankfurt, Berlin, grid queues and hiring

By the Workfully data centre hiring team · Last reviewed

Summary

Data centres in Germany are concentrated in Frankfurt, where power, not demand, now sets the pace. Frankfurt has 970 MW installed and a vacancy rate of 3.1%, and grid operators quote capacity for current applications only from the mid-2030s (JLL, Aug 2026).

Key facts

  • Frankfurt is continental Europe's largest data centre market, with 970 MW of installed capacity and a vacancy rate of 3.1% in 2026. (JLL, 24 August 2026)
  • Frankfurt has 311 MW under construction and 687 MW in planning, the largest development pipeline in Europe. (JLL, 24 August 2026)
  • Cushman & Wakefield ranks Frankfurt third worldwide among markets with particularly low short-term availability. (Cushman & Wakefield, 29 May 2026)
  • Berlin has grown to 148 MW of capacity with a vacancy rate of 0.9%, plus 143 MW under construction and 379 MW planned. (JLL, 24 August 2026)
  • Germany reports shortages of building electricians, electrical engineers, electrical fitters and air conditioning and refrigeration mechanics in the 2025 EURES labour shortages report. (European Labour Authority, June 2026)

Germany's data centre (data center in US usage) market is mostly a Frankfurt story, and Frankfurt is short of power rather than demand. Frankfurt is one of seven "Powerhouse" markets in Cushman & Wakefield's EMEA index, while Berlin is classed as a secondary market (Cushman & Wakefield, Sep 2026). For hiring teams, the useful question is which projects will actually get power, and when.

How big is the German data centre market in 2026?

JLL put Germany's operational data centre IT capacity at about 1.3 GW in April 2026, rising to as much as 3.3 GW by 2029 (JLL, Apr 2026). Frankfurt is the largest German market, with 970 MW installed in JLL's later count (JLL, Aug 2026). The five FLAP-D markets of Frankfurt, London, Amsterdam, Paris and Dublin together hold about 5.2 GW of operational capacity, roughly 43% of the EMEA total (Cushman & Wakefield, Sep 2026).

Market Installed or operational capacity Under construction Planned Vacancy Stated constraint Source
Frankfurt 970 MW installed 311 MW 687 MW 3.1% Grid capacity for current applications only from the mid-2030s, per grid operators JLL, Aug 2026
Berlin 148 MW 143 MW 379 MW 0.9% Market effectively fully let JLL, Aug 2026

The city figures come from a later JLL report than the national total, so do not add them up.

Why is Frankfurt so tight?

New supply is let quickly. Frankfurt took up 128 MW in a record 2025 and 36 MW in the first half of 2026 (JLL, Aug 2026). Its 3.1% vacancy is under half the FLAP-D average (JLL, Aug 2026).

Cushman & Wakefield ranks Frankfurt third worldwide among markets with particularly low short-term availability, and reports exceptionally high pre-leasing of planned data centres (Cushman & Wakefield, May 2026). It expects growth to become more selective, energy-driven and dependent on permitting.

How long does a grid connection take in Frankfurt?

Longer than most build programmes. JLL reports that grid connections for sites of 50 MW or more in the Rhine-Main region now take up to 13 years (JLL, Apr 2026). Grid operators say capacity for current applications is available only from the mid-2030s (JLL, Aug 2026).

This is part of a wider pattern: across EMEA, power availability, permitting and grid capacity increasingly decide where new data centres can be built (Cushman & Wakefield, Sep 2026).

Projects that already hold power still move. JLL notes that Frankfurt's 311 MW in development and 687 MW planned are paced by lead times of 24 months or more (JLL, Aug 2026). That split matters for hiring: a site with a connection date has a real build programme, while one waiting for a new connection does not yet need a site team.

What do Germany's energy efficiency rules mean for new sites?

Germany's Energy Efficiency Act (Energieeffizienzgesetz, EnEfG) sets rules for data centres by start-of-operation date. Operators must buy renewable power to match their use, on an annual balance. That is half from 1 January 2024 and all of it from 1 January 2027 (Energy Efficiency Act, section 11).

A data centre starting operation from 1 July 2026 must reach a power usage effectiveness (PUE) of 1.2 or better (Energy Efficiency Act, section 11). It must also reuse at least 10% of its energy (Energy Efficiency Act, section 11). The planned reuse share rises to 15% for sites starting from 1 July 2027 and 20% from 1 July 2028 (Energy Efficiency Act, section 11).

Existing sites must reach a PUE of 1.5 from 1 July 2027 and 1.3 from 1 July 2030 (Energy Efficiency Act, section 11). Meeting the reuse and efficiency requirements means designing for heat recovery and efficient cooling from the start. That brings mechanical, heat-network and energy-reporting skills into the design and operations brief, alongside the usual critical-power roles. Confirm the current text with counsel before fixing a site's design or job descriptions around it.

Which skills are in short supply in Germany?

The trades and engineers that build and run data centres are already scarce. In the 2025 EURES report, Germany reports shortages in several occupations that map directly to data centre teams (European Labour Authority, Jun 2026).

Occupation (EURES classification) Germany reports a shortage? Typical data centre roles Source
Building and related electricians Yes Electrical installation, site electricians, electrical supervisors European Labour Authority, Jun 2026
Electrical engineers Yes Electrical leads, commissioning engineers, authorised persons European Labour Authority, Jun 2026
Electrical engineering technicians Yes Critical facilities technicians, shift engineers European Labour Authority, Jun 2026
Electrical mechanics and fitters Yes Switchgear and generator maintenance European Labour Authority, Jun 2026
Air conditioning and refrigeration mechanics Yes Cooling technicians, mechanical shift engineers European Labour Authority, Jun 2026
Construction managers and supervisors Yes Construction managers and site supervisors European Labour Authority, Jun 2026

The role mapping is a guide for hiring teams, not part of the EURES classification.

The same report shows where the surplus sits. Greece, Finland and Latvia report surpluses of electrical engineers (European Labour Authority, Jun 2026). Across Europe, 98% of occupations short in at least one country are in surplus in another (EURES, Jun 2026).

What does this mean for hiring teams?

Hiring in Germany follows power dates more than construction plans. Frankfurt projects compete for the same electrical people. Germany already reports shortages of electricians and electrical engineers (European Labour Authority, Jun 2026). Berlin's pipeline adds a second centre of demand.

Across EMEA, JLL reports that hyperscale projects planned for 2026 to 2028 sit 175 km from the main hubs on average (JLL, Aug 2026). Those finished in 2022 to 2025 sit 46 km away (JLL, Aug 2026). Some site teams may therefore be needed outside Frankfurt and Berlin.

Cross-border sourcing is part of the answer, but language and qualifications need early decisions. Where a role handles German-language permits, safety documents or local contractors, fluent German may be essential; other roles may work in English.

Checklist for staffing a German data centre site:

  1. Confirm the grid connection date with the network operator before opening senior searches.
  2. Separate projects with secured power from those still in the queue, and staff only the first group for construction.
  3. Map each hire to its phase: design, construction, commissioning or operations.
  4. Decide which roles need fluent German and which can run in English.
  5. Add heat-reuse and energy-reporting skills to the mechanical and operations briefs.
  6. Check which nearby Frankfurt or Berlin projects will compete for the same electrical supervisors.
  7. Plan cross-border searches for electrical engineers early.
  8. Hire the future site manager before handover, so they learn the plant during commissioning.

For pay benchmarks, see data centre manager salaries in the UK, US and Germany. For the role that manages power dates, see the grid connection manager. For other European hotspots, see the briefs on data centres in the Nordics, data centres in Spain and Portugal and data centres in the Netherlands.

Hiring for a data centre in Germany? Workfully is an AI-native recruiting partner built around your hiring needs. Senior specialist recruiters deliver the hires your business needs without scaling your recruiting team. Your team interviews and decides (Workfully for data centres).

Frequently asked questions

How much data centre capacity is there in Germany?
JLL put Germany's operational data centre IT capacity at about 1.3 GW in April 2026 and expects up to 3.3 GW by 2029 (JLL, Apr 2026). Frankfurt is the largest German market and one of seven Powerhouse markets in Cushman & Wakefield's EMEA index (Cushman & Wakefield, Sep 2026). Berlin is the main secondary market.
Why is it hard to build new data centres in Frankfurt?
Power is the main limit. Across EMEA, power availability, permitting and grid capacity increasingly decide where new data centres can be built (Cushman & Wakefield, Sep 2026). Cushman & Wakefield describes Frankfurt as a high-demand but power-constrained market where growth will be more selective and dependent on permitting (Cushman & Wakefield, May 2026).
Is Berlin an alternative to Frankfurt for data centres?
JLL describes Berlin as an established alternative location. It has 148 MW of capacity, a vacancy rate of 0.9%, 143 MW under construction and 379 MW planned (JLL, Aug 2026). Cushman & Wakefield lists Berlin as a secondary market in its EMEA index (Cushman & Wakefield, Sep 2026). The pipeline is large relative to the live base, so build-phase hiring there is likely to grow first.
Which data centre roles are hardest to fill in Germany?
In the EURES 2025 report, Germany reports shortages of electricians, electrical engineers and technicians, electrical fitters and refrigeration mechanics (European Labour Authority, Jun 2026). Those trades and engineers make up much of a build and operations team.

Sources

  1. JLL. KI-Boom verändert europäische Rechenzentrumslandschaft (AI boom reshapes the European data centre landscape). Published . Accessed . Tier B, research and press.
  2. JLL. EMEA data centre mid-year 2026 report. Published . Accessed . Tier B, research and press.
  3. JLL. Die neue Geografie des Rechenzentrumsmarktes in Deutschland (The new geography of the German data centre market). Published . Accessed . Tier B, research and press.
  4. Bundesministerium der Justiz (gesetze-im-internet.de). Gesetz zur Steigerung der Energieeffizienz in Deutschland (Energieeffizienzgesetz, EnEfG), § 11 Klimaneutrale Rechenzentren (Energy Efficiency Act, section 11: climate-neutral data centres). Published . Accessed . Tier A, primary.
  5. Cushman & Wakefield. Global Data Center Market Comparison 2026. Published . Accessed . Tier B, research and press.
  6. Cushman & Wakefield. European Data Centre capacity surpasses 12GW. Published . Accessed . Tier B, research and press.
  7. Cushman & Wakefield. H1 2026 EMEA Data Centre Market Update. Published . Accessed . Tier B, research and press.
  8. European Labour Authority. EURES – Report on labour shortages and surpluses 2025, Annex: Transnational matching possibilities. Published . Accessed . Tier A, primary.
  9. EURES (European Commission). What the latest data reveals about labour market imbalances across Europe. Published . Accessed . Tier A, primary.