How to hire
How long does it take to build a data centre, and when to hire?
By the Workfully data centre hiring team · Last reviewed
Summary
How long it takes to build a data centre depends more on power than on construction. JLL puts the average global build time for a 50 MW data centre at 18 months, while grid connections in primary markets average over four years (JLL, Jan 2026). Hiring dates should follow energisation and commissioning dates.
Key facts
- The average global build time for a 50 MW data centre is 18 months, according to JLL's 2026 outlook. (JLL, January 2026)
- The average wait for a grid connection in primary data centre markets exceeds four years, according to JLL. (JLL, January 2026)
- 57% of data centre projects experienced a construction delay of three months or more in 2025, according to JLL. (JLL, January 2026)
- Power transformers averaged 128 weeks from order to delivery in Wood Mackenzie's second-quarter 2025 survey, as reported by POWER. (POWER, 2 January 2026)
- The Associated Builders and Contractors trade group estimates the US construction industry needs about 349,000 new workers in 2026 and about 500,000 in 2027. (CNBC, 18 March 2026)
A data centre (data center in US usage) is usually planned around its construction programme, but power and equipment decide when it can go live. Hiring plans built from the ground-breaking date tend to run late. Plans built backwards from energisation and commissioning dates hold up better.
How long does it take to build a data centre?
The construction phase is the shortest part of the timeline. The average global build time for a 50 MW data centre is 18 months (JLL, Jan 2026).
That figure assumes the site has land, permits, power and equipment lined up. Before ground is broken, the project has usually spent years securing a grid connection and planning consent.
Community engagement adds to the front end. JLL says current industry practice is to begin community consultation 6 to 18 months into the development process (JLL, Jan 2026). It recommends predevelopment engagement timelines of up to 24 months instead (JLL, Jan 2026).
Slippage is common once building starts. 57% of data centre projects experienced a construction delay of three months or more in 2025 (JLL, Jan 2026).
Why does power, not construction, set the timeline?
A building can be finished long before the grid can supply it. The average wait for a grid connection in primary data centre markets exceeds four years (JLL, Jan 2026).
Across a wider set of projects, waits are shorter but still long. In Turner & Townsend's 2026 survey, 53% of respondents said utility connections take between one and two years, and a further 32% reported more than two years (Turner & Townsend, 2026). The same survey found 56% name power as a major obstacle to successful delivery (Turner & Townsend, 2026).
Queues are crowded in some markets. In Great Britain, contracted demand offers rose from 41 GW to 125 GW between November 2024 and June 2025, driven largely by data centre projects (Ofgem, Jul 2026). Ofgem has proposed data-centre-specific milestones that would require developers to show tangible progress to keep their place.
For hiring, the confirmed energisation date matters more than the construction start. Commissioning cannot finish without permanent power, and the operations team cannot take over a site that has not been through integrated testing. For GPU-cloud sites, see how neoclouds build a data centre team.
Which equipment lead times affect hiring dates?
Long-lead electrical equipment fixes the middle of the timeline. The average lead time for data centre equipment is 33 weeks globally, and 42 weeks in the US (JLL, Jan 2026).
Large transformers take far longer. Power transformers averaged 128 weeks and generator step-up units 144 weeks in Wood Mackenzie's second-quarter 2025 survey (POWER, Jan 2026).
Developers respond by ordering early. JLL reports developers preordering select materials as much as 24 months in advance (JLL, Jan 2026). Operators of scale hold 6 to 12 months of strategic inventory for critical components (JLL, Jan 2026).
Early orders need people to manage them. Bring in the electrical package manager and the owner's electrical lead before transformer, switchgear and generator orders are placed. Their job is to fix specifications, track factory tests and plan deliveries against the programme.
Supply chains add their own risk. 64% of respondents in Turner & Townsend's 2026 survey describe their local supply chain as moderately, highly or severely constrained (Turner & Townsend, 2026).
When should each team be hired?
The planner below sets each build phase against a sourced timing signal, the roles to have in seat and the event that should trigger the hire. The roles and triggers are a synthesis for hiring teams, not recommendations from the sources.
| Phase | Sourced timing signal | Roles to have in seat | Hire-by trigger | Source |
|---|---|---|---|---|
| Site and power | Grid connection waits in primary markets average over four years | Owner's project director, grid connection and high-voltage lead | Before the connection application and land deal are committed | JLL, Jan 2026 |
| Design | Commissioning provider under contract by the start of design development | Design manager, commissioning provider or commissioning lead | Before design development starts | GSA, Sep 2020 |
| Procurement | Power transformers averaged 128 weeks in Wood Mackenzie's Q2 2025 survey | Owner's electrical lead, procurement lead, electrical installation manager | Before long-lead orders are placed | POWER, Jan 2026 |
| Construction | Average global build time of 18 months for a 50 MW site | Construction manager, mechanical and electrical installation leads, quality leads | Before the main contractor mobilises | JLL, Jan 2026 |
| Commissioning | Most owner training should happen during construction, before substantial completion | Commissioning engineers, operations manager, shift leads and engineers | Before training and integrated testing begin | GSA, Sep 2020 |
| First year of operation | Performance reviewed 10 months into a 12-month warranty period | Full facility team, maintenance planners, controls specialists | Before the first customer load | GSA, Sep 2020 |
| Steady state | Operators name junior and mid-level operations staff among the roles with the highest turnover | Backfill pipeline for operations roles | Before the first anniversary of go-live | Uptime Institute, Oct 2025 |
For headcount at each phase rather than timing, see the guide to how many people a data centre needs to build and run.
When does the commissioning team need to start?
Commissioning begins on paper long before equipment is energised. The US General Services Administration's commissioning guide says the commissioning provider should be under contract by the beginning of design development (GSA, Sep 2020). On design-build projects, it says to retain one during the planning phase.
The operations team needs time on site before handover. The same guide says the majority of training should be done during the construction phase, before substantial completion (GSA, Sep 2020). Staff hired after that point learn the plant once it already carries a live load.
Commissioning also continues after go-live. The guide describes deferred and seasonal testing, and a critical review of systems 10 months into a 12-month warranty period (GSA, Sep 2020). Someone on the permanent team has to own that review.
The five commissioning levels and integrated systems testing explain which tests each hire will join.
What happens to the hiring plan when the build slips?
Delays move the go-live date, and hiring has to move with it. A shortage of qualified staff can itself delay projects and make operations harder to manage, according to Uptime Institute (Uptime Institute, Jul 2026).
Candidates are scarce, so waiting for certainty carries its own risk. One recruitment executive told POWER magazine that electrical engineers and commissioning professionals are "some of the hardest roles to fill right now" (POWER, Sep 2026). The wider trades market is tight too: the Associated Builders and Contractors trade group estimates the US construction industry needs about 349,000 new workers in 2026 (CNBC, Mar 2026).
Demand for the same people is rising. Randstad found that job listings for skilled trades such as construction workers and electricians rose 27% between 2022 and 2026 (CNBC, Mar 2026). A plan that holds critical hires until the last month leaves no room for a failed search.
The practical answer is to separate hires by trigger. Leadership and package roles track the procurement and construction programme. Operations roles track the confirmed energisation and integrated testing dates, and move only when those dates move.
Build timeline hiring checklist
Use this list to turn a project programme into hiring dates. Each item is a decision for the hiring team, drawn from the sourced points above.
- Record the confirmed grid energisation date, and the source of that date.
- List every long-lead equipment order, with its order date and expected delivery.
- Name the owner's lead for each long-lead package before its order is placed.
- Confirm the commissioning provider is appointed before design development starts.
- Set the date integrated testing begins, and date every operations hire back from it.
- Allow for notice periods, site access, security clearance and induction in each hire date.
- Plan operator training during construction, not after handover.
- Name the person who owns deferred testing and the warranty review in the first year.
- Agree which hires move if the energisation date slips, and which stay fixed.
How do you back-schedule hires from go-live?
Work backwards from the dates that cannot move without the grid or the equipment.
- Fix the energisation date and the start of integrated testing.
- Place operations leads and shift engineers early enough to train during construction.
- Place commissioning engineers ahead of the first equipment start-up.
- Place package managers before their work is ordered or mobilised.
- Place the commissioning provider before design development.
- Review the whole plan each time the programme changes.
To brief a recruiter on this kind of search, see how to brief a data centre recruiter. For the engagement options, see data centre hiring models.
Hiring for a build on a fixed energisation date? Workfully is an AI-native recruiting partner built around your hiring needs. Senior specialist recruiters deliver the hires your business needs without scaling your recruiting team. Your team interviews and decides (Workfully for data centres).
Frequently asked questions
- Can a data centre be built faster than 18 months?
- Some can, mainly with prefabricated modules. JLL says modular systems allow faster install schedules, and that hyperscale campuses may achieve sub-12-month deployments by 2030 (JLL, Jan 2026). A faster build compresses the hiring plan rather than removing it: commissioning and operations hires still need to be in seat before integrated testing.
- What usually delays a data centre build?
- Power and equipment are the usual culprits. Turner & Townsend's 2026 survey found 56% of respondents name power as a major obstacle to successful delivery (Turner & Townsend, 2026). JLL reports that developers preorder select materials as much as 24 months ahead to avoid delays (JLL, Jan 2026). A shortage of qualified people can also hold a project back.
- Should operations staff be hired before construction finishes?
- Yes, for the people who will run the plant. The US General Services Administration's commissioning guide says most owner training should happen during construction, before substantial completion (GSA, Sep 2020). Operations leads and shift engineers hired after handover miss that training and the integrated tests that show how the site behaves under failure.
- Where do new data centre operations hires come from?
- Often from outside the industry. Universities were the most-cited source of new data centre hires over the previous 12 months, named by 50% of operators in Uptime Institute's 2025 staffing survey (Uptime Institute, Oct 2025). Graduates and adjacent-industry hires need experienced shift leads in place first, which pushes the senior operations hires earlier in the timeline.
Related articles
How to hire
How many people does a data centre need to build and run?
How many employees a data center has by phase: why construction crews far outnumber the permanent team, how to size 24/7 operations cover, and when to hire.
Last reviewed
Role explainers
Data centre roles: an org chart across four hiring lanes
Data center roles mapped to four lanes: power and energy, construction and MEP, white space and IT, and critical operations, with the build phase of each role.
Last reviewed
How to hire
How to brief a data centre recruiter: a checklist for hiring managers
A checklist for briefing a data center recruiter: role lane, site and candidate markets, credentials, interview process, decision-makers and search sequence.
Last reviewed
How to hire
Agency, search or recruitment process outsourcing for a data centre?
How agency recruitment, executive search, recruitment process outsourcing and managed services work, and how to match each model to a data center hire.
Last reviewed
Sources
- JLL. 2026 Global Data Center Outlook: Navigating AI demand, power constraints and global opportunities in 2026. Published . Accessed . Tier B, research and press.
- Turner & Townsend. Data centre construction cost index 2026: Industry challenges. Published . Accessed . Tier B, research and press.
- POWER. Transformers in 2026: Shortage, Scramble, or Self-Inflicted Crisis?. Published . Accessed . Tier B, research and press.
- Ofgem. Ofgem acts to free up grid capacity by tackling speculative data centre projects. Published . Accessed . Tier A, primary.
- Uptime Institute. Uptime Institute Global Data Center Survey 2026 (keynote report PDF). Published . Accessed . Tier A, primary.
- Uptime Institute. Data Center Staffing and Hiring Survey Findings, October 2025 summary. Published . Accessed . Tier A, primary.
- US General Services Administration. GSA Commissioning Guide. Published . Accessed . Tier A, primary.
- POWER magazine. The POWER Interview: How the Data Center Power Crunch Is Reshaping the Talent Market. Published . Accessed . Tier B, research and press.
- CNBC. How the red-hot AI data center boom is igniting demand for a new, lucrative career path: Trade workers. Published . Accessed . Tier B, research and press.
