How many people does a data centre need to build and run?
By the Workfully data centre hiring team · Last reviewed
Summary
How many employees a data centre has depends on the phase. Construction brings the largest workforce, while the permanent team is sized from 24/7 shift cover and maintenance hours by trade. Filling it is the hard part: electrical engineers and commissioning professionals are among the hardest roles to fill (POWER, Sep 2026).
Key facts
- A recruitment executive told POWER magazine that electrical engineers and commissioning professionals are among the hardest data centre roles to fill. (POWER magazine, 3 September 2026)
- Randstad found that job listings for skilled trades such as construction workers and electricians rose 27% between 2022 and 2026. (CNBC, 18 March 2026)
- In Uptime Institute's 2025 staffing survey, 57% of operators named junior and mid-level operations staff among the roles with the highest turnover. (Uptime Institute, October 2025)
- Universities were the most-cited source of new data centre hires over the previous 12 months, named by 50% of operators in Uptime Institute's 2025 staffing survey. (Uptime Institute, October 2025)
- The Lanarkshire AI Growth Zone is projected to support more than 3,400 jobs, around 800 of them expected to focus on AI. (GOV.UK, Department for Science, Innovation and Technology, 29 January 2026)
A data centre (data center in US usage) needs its largest workforce while it is being built, and a much smaller permanent team once it is live. Treating those as one number is the most common planning mistake. Each phase has a different employer, different roles and a different lead time.
How many employees does a data centre have once it is running?
The permanent team is small next to the build workforce. When CloudHQ's Didcot campus was announced, the government said it would create 1,500 jobs during construction and 100 permanent jobs once fully operational (GOV.UK, Oct 2024). That is 15 construction jobs announced for every permanent post, as of October 2024 (GOV.UK, Oct 2024).
Large AI campuses publish bigger totals with the same mix. The Lanarkshire AI Growth Zone is projected to support more than 3,400 jobs (GOV.UK, Jan 2026). The announcement describes roles running through to permanent staff who will run and maintain the data centres (GOV.UK, Jan 2026). Around 800 of those jobs are expected to focus on AI (GOV.UK, Jan 2026).
The permanent team is also wider than the engineers on shift. Uptime Institute groups data centre staffing into facility, IT and security operations (Uptime Institute Journal, Mar 2015). A site that plans only the facility team will find the other two missing at handover.
Announced job totals are projections from governments and developers, not staffing plans. The plan an operator needs is built bottom-up, from the work each phase requires. The same applies to GPU-cloud developers, covered in how neoclouds build a data centre team.
Why does construction need far more people than operations?
Construction converts power and cooling designs into installed plant, and very large sites now mean gigawatts of electrical infrastructure. Uptime Institute links very large builds to a large demand for electricians, when many regions already lack qualified electrical workers (Uptime Institute, Jul 2026).
The pressure shows up in the wider trades market. Randstad found that job listings for skilled trades such as construction workers and electricians rose 27% between 2022 and 2026 (CNBC, Mar 2026).
AI campuses add to the load. Uptime says large, specialised AI facilities require more staff for major new projects and new skill sets for higher thermal densities (Uptime Institute, Jul 2026).
Most of the construction peak is employed by contractors, not the owner. The owner's hiring plan should focus on the people who lead and check that work: the project director, package managers, the commissioning lead and the first operations managers.
Who needs to be on site during commissioning?
Operations should not wait for handover. Uptime Institute guidance says the owner should hire the data centre facility manager and one facility supervisor at pre-design, to represent operations through commissioning (Uptime Institute Journal, May 2015). ASHRAE also says the owner's operations and maintenance staff should help develop the owner's project requirements during predesign (ASHRAE Handbook, 2019).
The same guidance says the entire operations team does not need to be in place for construction and commissioning (Uptime Institute Journal, May 2015). What matters is that operations and the commissioning authority write the Level 4 and Level 5 scripts together. Systems are then tested the way the site will actually be run and maintained.
Leaving operations out is costly. The guidance calls it "a huge missed opportunity for training" (Uptime Institute Journal, May 2015). After turnover, operations uses the commissioning results to finalise its standard, method and emergency operating procedures, and the site carries more risk until that is done.
For hiring, this sets the real deadline. Shift engineers who will run the plant need to be hired, cleared and on site in time for integrated testing. That comes well before the first customer load.
How do you calculate the permanent operations headcount?
Uptime Institute's method starts with two inputs: annual maintenance hours by trade, and the shift-presence hours the business objective requires (Uptime Institute Journal, Mar 2015). The total is then divided by the productive hours each person has available in a year.
The result is rarely a whole number. Uptime suggests covering the fraction with overtime, kept below 10% (as of March 2015, Uptime Institute Journal). Anything above that is a hiring gap, not an overtime plan.
Shift presence sets the floor. Uptime's operational certification requires at least one qualified full-time staff presence per shift, 24/7, at Tier III, and two at Tier IV (Uptime Institute Journal, Apr 2020). Every seat that must be filled around the clock needs several people behind it once nights, weekends, leave and training are counted.
Shift work and maintenance overlap. Rounds and building management system monitoring do not usually need every hour of a shift, so maintenance tasks can be planned into the spare time (Uptime Institute Journal, Mar 2015).
Shift length changes the rota. Most operators in Uptime's 2025 staffing survey reported typical single-day shifts of 8–10 hours (Uptime Institute, Oct 2025). Uptime advises avoiding shifts of more than 12 hours (Uptime Institute Journal, May 2024). The UK Health and Safety Executive's good-practice guidance says to limit shifts to 12 hours including overtime, and to 8 hours for night work and for demanding, monotonous, dangerous or safety-critical work (HSE, Oct 2024).
Headcount alone does not make a safe team. In Uptime assessments, staffing numbers were inadequate in only 7% of data centres, but qualifications were inadequate in twice as many (as of March 2015, Uptime Institute Journal). Size the team, then check that enough of it is qualified to act alone on every shift.
How should a new campus be staffed, phase by phase?
The planner below sets each phase against who leads the hiring, which roles need to be in seat and the sourced signal behind it. The phases and actions are a synthesis for hiring teams, not Uptime recommendations.
| Phase | Who leads the hiring | Roles to have in seat | Sourced signal | Source |
|---|---|---|---|---|
| Pre-design and design | Owner | Facility manager and one facility supervisor, representing operations | Both hired at pre-design, per Uptime guidance | Uptime Institute Journal, May 2015 |
| Construction | Contractors, led by the owner's project team | Project director, electrical and mechanical leads, construction managers, site trades | Announced construction jobs far exceed permanent ones, as the Didcot figures above show | GOV.UK, Oct 2024 |
| Commissioning | Owner and commissioning authority | Commissioning engineers, plus the operations staff who will run the site | Operations and the commissioning authority write the Level 4 and Level 5 scripts | Uptime Institute Journal, May 2015 |
| Handover | Owner | Full facility team, ready to finalise operating procedures | Commissioning results feed standard, method and emergency procedures | Uptime Institute Journal, May 2015 |
| Day-2 operations | Owner or operations contractor | Shift engineers for round-the-clock cover, maintenance trades, IT and security | At least one qualified person per shift at Tier III, two at Tier IV | Uptime Institute Journal, Apr 2020 |
| Steady state | Owner | Backfill and a pipeline for junior and mid-level operations roles | 57% of operators name these roles among those with the highest turnover | Uptime Institute, Oct 2025 |
Where will the operations team come from?
Experienced operators are scarce. One recruitment executive told POWER magazine that electrical engineers and commissioning professionals are "some of the hardest roles to fill right now" (POWER, Sep 2026). Operator survey detail is in the skills gap guide.
New hires increasingly come from outside the industry. Universities were the most-cited source of new data centre hires, named by 50% of operators in Uptime's 2025 staffing survey (Uptime Institute, Oct 2025). Uptime expects operators to recruit and train from universities, trade schools and industries with overlapping skill sets (Uptime Institute, Jul 2026).
Local training routes are being built alongside some campuses. The Lanarkshire AI Growth Zone includes 50 apprenticeships (GOV.UK, Jan 2026). Apprentices and graduates still need experienced shift leads to learn from, so the senior hires come first.
Turnover keeps the search open after go-live. 34% of operators said their number of new data centre hires had increased in 2025 (Uptime Institute, Oct 2025). Operations management was the second most-cited high-turnover role, named by 30% (Uptime Institute, Oct 2025).
What should a campus staffing plan include?
Use this checklist before the first search opens. Each item turns a sourced point above into a decision the hiring team can own.
- Separate the construction peak from the permanent team, and name the employer for each role.
- Hire the facility manager and a facility supervisor at pre-design, not at handover.
- List the owner's leadership hires for the build: project director, package managers and commissioning lead.
- Set the shift presence the business needs, then confirm the minimum qualified cover for the target Tier.
- Total the annual maintenance hours by trade and add the shift-presence hours.
- Divide by productive hours per person, and treat any gap beyond modest overtime as a hire.
- Plan facility, IT and security operations together, so none is missing at go-live.
- Date every operations hire back from integrated testing, allowing time for notice periods, site access and training.
- Build a pipeline for junior and mid-level operations roles from universities, trade schools and adjacent industries.
- Pair every group of new entrants with experienced shift leads before the site carries a live load.
Staffing a new campus? Workfully is an AI-native recruiting partner built around your hiring needs. Senior specialist recruiters deliver the hires your business needs without scaling your recruiting team. Your team interviews and decides (Workfully for data centres).
Frequently asked questions
- How many people are on site at a data centre overnight?
- It depends on the resilience the business needs. Uptime Institute's operational certification requires at least one qualified full-time person per shift around the clock at Tier III, and two at Tier IV (Uptime Institute Journal, Apr 2020). Those are minimums for the facility team. Security and IT cover are planned separately, and maintenance work may add people to particular shifts.
- When should a new data centre hire its facility manager?
- Earlier than most owners expect. Uptime Institute guidance says the owner should hire the facility manager and one facility supervisor at pre-design, to represent operations through the project (Uptime Institute Journal, May 2015). The rest of the operations team can follow later, but early enough to take part in integrated testing before handover.
- Do AI data centres need more staff than conventional sites?
- Uptime Institute says large, specialised AI facilities require more staff for major new projects, and evolving skill sets to support higher thermal densities (Uptime Institute, Jul 2026). In practice, that means more electrical and mechanical depth during the build, and operations engineers who understand liquid cooling and high-density power once the site is live.
- Can a new campus hire operations staff from outside the data centre industry?
- Yes, and most will have to. Uptime Institute expects operators to recruit and train staff from universities, trade schools and industries with overlapping skill sets (Uptime Institute, Jul 2026). Pair adjacent-industry hires with experienced shift leads, and get them on site during commissioning, so they learn the plant before it carries a live load.
Related articles
Market briefs
UK data centres in 2026: capacity, power and the people behind them
London data centre space and power in 2026: 1.38 GW live, a 1.77 GW pipeline, the west London grid squeeze and what the power limit means for hiring teams.
Last reviewed
Market briefs
UK AI Growth Zones: sites, megawatts and the people to staff them
UK AI Growth Zones explained: the five announced sites, their power plans, the construction and permanent jobs they project, and what it means for hiring teams.
Last reviewed
How to hire
How to brief a data centre recruiter: a checklist for hiring managers
A checklist for briefing a data center recruiter: role lane, site and candidate markets, credentials, interview process, decision-makers and search sequence.
Last reviewed
How to hire
Agency, search or recruitment process outsourcing for a data centre?
How agency recruitment, executive search, recruitment process outsourcing and managed services work, and how to match each model to a data center hire.
Last reviewed
Sources
- Uptime Institute. Uptime Institute Global Data Center Survey 2026 (keynote report PDF). Published . Accessed . Tier A, primary.
- Uptime Institute. Data Center Staffing and Hiring Survey Findings, October 2025 summary. Published . Accessed . Tier A, primary.
- Uptime Institute Journal. Proper data center staffing is key to reliable operations. Published . Accessed . Tier A, primary.
- Uptime Institute Journal. COVID-19: Q&A (Part 1): Staff management. Published . Accessed . Tier A, primary.
- Uptime Institute Journal. Long shifts in data centers — time to reconsider?. Published . Accessed . Tier A, primary.
- Uptime Institute Journal. Improve project success through mission critical commissioning. Published . Accessed . Tier A, primary.
- GOV.UK, Department for Science, Innovation and Technology. Tech Secretary welcomes foreign investment in UK data centres which will spur economic growth and AI innovation in Britain. Published . Accessed . Tier A, primary.
- GOV.UK, Department for Science, Innovation and Technology. More than 3,400 jobs and targeted support for local communities to help tackle the cost of living as Lanarkshire named latest AI Growth Zone. Published . Accessed . Tier A, primary.
- POWER magazine. The POWER Interview: How the Data Center Power Crunch Is Reshaping the Talent Market. Published . Accessed . Tier B, research and press.
- CNBC. How the red-hot AI data center boom is igniting demand for a new, lucrative career path: Trade workers. Published . Accessed . Tier B, research and press.
- ASHRAE. HVAC commissioning (ASHRAE Handbook: HVAC Applications, chapter 44). Published . Accessed . Tier A, primary.
- Health and Safety Executive (UK). Good practice guidelines (shift work and fatigue). Published . Accessed . Tier A, primary.