  "title": "Data centres in Spain and Portugal: Madrid, Aragón, Lisbon, Sines",
  "url": "https://globaldatacentertalent.com/articles/iberia-talent",
  "description": "Iberia added 65 MW IT of live data centre capacity in six months to September 2026. A brief on Madrid, Aragón, Lisbon, Sines, grid access and site hiring.",
  "type": "market-brief",
  "cluster": "market-region-briefs",
  "market": "eu",
  "publishedAt": "2026-11-16",
  "lastReviewed": "2026-11-16",
  "dateModified": "2026-11-16",
  "author": "Workfully data centre hiring team",
  "summary": "Data centres in Spain and Portugal are moving from a small live base to a large pipeline, with grid access setting the pace. Iberia had about 450 MW IT operational in September 2026, up 65 MW IT in six months ([Colliers, Oct 2026](https://www.colliers.com/es-es/research/data-center-snapshot-iberian-region-april-2026-sept-2026)). Spanish data centres hold 6,329 MW of granted grid access, none in service ([Red Eléctrica, Oct 2026](https://www.ree.es/es/sala-de-prensa/actualidad/nota-de-prensa/2026/10/red-electrica-publica-el-mapa-de-capacidades-de-demanda-tipo-consumo)).",
  "keyFacts": [
    {
      "text": "Operational data centre capacity across Spain and Portugal reached about 450 MW IT in September 2026, up 65 MW IT in six months.",
      "source": "https://www.colliers.com/es-es/research/data-center-snapshot-iberian-region-april-2026-sept-2026"
    },
    {
      "text": "Data centres hold 6,329 MW, or 34.2%, of the transmission network access granted in Spain, and none of it is yet in service.",
      "source": "https://www.ree.es/es/sala-de-prensa/actualidad/nota-de-prensa/2026/10/red-electrica-publica-el-mapa-de-capacidades-de-demanda-tipo-consumo"
    },
    {
      "text": "Spain's ministry says grid access rights above 12 GW have been granted to data centres since 2021, against 3.5 to 4 GW of demand implied for 2030.",
      "source": "https://www.miteco.gob.es/es/prensa/ultimas-noticias/2026/agosto/-el-gobierno-plantea-impulsar-los-centros-de-datos-sostenibles--.html"
    },
    {
      "text": "CBRE puts the deliverable potential of the Iberian market at 4.5 GW of IT capacity over the medium term.",
      "source": "https://www.investinspain.org/en/news/2026/cbre"
    },
    {
      "text": "Operational colocation availability is 19% in Madrid and 14% in Barcelona, and falls to 9% in Madrid and nil in Barcelona for hyperscale and neocloud tenants.",
      "source": "https://www.colliers.com/es-es/research/data-center-snapshot-iberian-region-april-2026-sept-2026"
    },
    {
      "text": "In Turner & Townsend's 2026–27 data centre cost survey, 81% of respondents say skilled labour in their region is constrained.",
      "source": "https://www.turnerandtownsend.com/insights/data-centre-construction-cost-index-2026-27/"
    }
  ],
  "faq": [
    {
      "question": "How many data centres are there in Spain?",
      "answer": "Counts of buildings vary by tracker, so capacity is the better measure. Colliers puts operational capacity across Spain and Portugal at about 450 MW IT in September 2026, led by Madrid at 212 MW IT ([Colliers, Oct 2026](https://www.colliers.com/es-es/research/data-center-snapshot-iberian-region-april-2026-sept-2026))."
    },
    {
      "question": "Where are the largest data centre projects in Spain?",
      "answer": "Aragón holds the largest single-region pipeline, at 3,764 MW IT planned ([Colliers, Oct 2026](https://www.colliers.com/es-es/research/data-center-snapshot-iberian-region-april-2026-sept-2026)). AWS announced 33.7 billion euros of investment in Spain in March 2026, with sites in Teruel, Huesca and Zaragoza ([Spanish government, Mar 2026](https://digital.gob.es/comunicacion/notas-prensa/mtdfp/2026/03/el-gobierno-celebra-la-apuesta-de-amazon-por-espana-con-una-inve))."
    },
    {
      "question": "Is Sines the largest data centre project in Portugal?",
      "answer": "JLL describes Start Campus at Sines as the largest hyperscale project in development in Portugal, with a final target of 1,200 MW ([JLL, Sep 2026](https://www.jll.com/pt-pt/newsroom/boom-da-ia-e-restricoes-energeticas-na-europa-colocam)). In the Lisbon region, JLL cites 1,300 MW of planned capacity, led by Merlin Edged's Vila Franca de Xira campus ([JLL, Sep 2026](https://www.jll.com/pt-pt/newsroom/boom-da-ia-e-restricoes-energeticas-na-europa-colocam))."
    },
    {
      "question": "Can new data centres get a grid connection in Portugal?",
      "answer": "Not on demand. In February 2026 Portugal recognised its whole mainland network territory as a single high-demand zone ([Diário da República, Feb 2026](https://diariodarepublica.pt/dr/detalhe/despacho/1135-2026-1031758691)). JLL describes a move from first-come, first-served allocation to financial guarantees, priority for strategic projects and capacity released in stages ([JLL, Sep 2026](https://www.jll.com/pt-pt/newsroom/boom-da-ia-e-restricoes-energeticas-na-europa-colocam))."
    },
    {
      "question": "Is there a shortage of data centre workers in Spain and Portugal?",
      "answer": "For specialist trades, yes. In Turner & Townsend's 2026–27 survey, 81% of respondents say skilled labour in their region is constrained, with MEP trades most sought-after ([Turner & Townsend, Oct 2026](https://www.turnerandtownsend.com/insights/data-centre-construction-cost-index-2026-27/)). In Portugal, JLL frames the task as turning data centre growth into qualified jobs ([JLL, Sep 2026](https://www.jll.com/pt-pt/newsroom/boom-da-ia-e-restricoes-energeticas-na-europa-colocam))."
    }
  ],
  "sources": [
    {
      "title": "Data Center Snapshot, Iberian Region, April 2026 – September 2026",
      "publisher": "Colliers",
      "url": "https://www.colliers.com/es-es/research/data-center-snapshot-iberian-region-april-2026-sept-2026",
      "published": "2026-10-08",
      "accessed": "2026-11-16",
      "tier": "B"
    },
    {
      "title": "Red Eléctrica publica el mapa de capacidades de acceso de la demanda por tipo de consumo",
      "publisher": "Red Eléctrica",
      "url": "https://www.ree.es/es/sala-de-prensa/actualidad/nota-de-prensa/2026/10/red-electrica-publica-el-mapa-de-capacidades-de-demanda-tipo-consumo",
      "published": "2026-10-01",
      "accessed": "2026-11-16",
      "tier": "A"
    },
    {
      "title": "El Gobierno plantea impulsar los centros de datos sostenibles, eficientes y soberanos",
      "publisher": "Ministerio para la Transición Ecológica y el Reto Demográfico (MITECO)",
      "url": "https://www.miteco.gob.es/es/prensa/ultimas-noticias/2026/agosto/-el-gobierno-plantea-impulsar-los-centros-de-datos-sostenibles--.html",
      "published": "2026-08-27",
      "accessed": "2026-11-16",
      "tier": "A"
    },
    {
      "title": "Despacho n.º 1135/2026, de 2 de fevereiro",
      "publisher": "Diário da República",
      "url": "https://diariodarepublica.pt/dr/detalhe/despacho/1135-2026-1031758691",
      "published": "2026-02-02",
      "accessed": "2026-11-16",
      "tier": "A"
    },
    {
      "title": "El Gobierno celebra la apuesta de Amazon por España con una inversión histórica de 33.700 millones de euros para impulsar centros de datos",
      "publisher": "Ministerio para la Transformación Digital y de la Función Pública",
      "url": "https://digital.gob.es/comunicacion/notas-prensa/mtdfp/2026/03/el-gobierno-celebra-la-apuesta-de-amazon-por-espana-con-una-inve",
      "published": "2026-03-02",
      "accessed": "2026-11-16",
      "tier": "A"
    },
    {
      "title": "Spain leads new European data centre era",
      "publisher": "Invest in Spain",
      "url": "https://www.investinspain.org/en/news/2026/cbre",
      "published": "2026-07-24",
      "accessed": "2026-11-16",
      "tier": "B"
    },
    {
      "title": "Start Campus avança em fevereiro com segundo edifício do centro de dados de Sines",
      "publisher": "RTP (Lusa)",
      "url": "https://www.rtp.pt/noticias/economia/start-campus-avanca-em-fevereiro-com-segundo-edificio-do-centro-de-dados-de-sines_n1709826",
      "published": "2026-01-13",
      "accessed": "2026-11-16",
      "tier": "B"
    },
    {
      "title": "Centros de Datos: ¿Qué ha cambiado en el borrador de Real Decreto?",
      "publisher": "Ashurst Perkins Coie",
      "url": "https://www.ashurstperkinscoie.com/es-es/insights/data-centres-what-has-changed-in-the-draft-royal-decree/",
      "published": "2026-11-03",
      "accessed": "2026-11-16",
      "tier": "B"
    },
    {
      "title": "Data Centers Iberian Region Snapshot, October 2025 – March 2026",
      "publisher": "Colliers",
      "url": "https://go.colliers.com/rs/427-KXE-423/images/Colliers_DC_Snapshot_Oct25_Mar26_.pdf",
      "published": "2026-04",
      "accessed": "2026-11-16",
      "tier": "B"
    },
    {
      "title": "Madrid ranks among the top five data center markets in EMEA",
      "publisher": "Cushman & Wakefield",
      "url": "https://www.cushmanwakefield.com/en/spain/news/2026/06/madrid-ranks-among-the-top-five-data-center-markets-in-emea",
      "published": "2026-06-15",
      "accessed": "2026-11-16",
      "tier": "B"
    },
    {
      "title": "European Data Centre capacity surpasses 12GW",
      "publisher": "Cushman & Wakefield",
      "url": "https://www.cushmanwakefield.com/en/netherlands/news/2026/09/europese-datacenter-capaciteit-passeert-de-12gw",
      "published": "2026-09-25",
      "accessed": "2026-11-16",
      "tier": "B"
    },
    {
      "title": "Data centre construction cost index 2026–27",
      "publisher": "Turner & Townsend",
      "url": "https://www.turnerandtownsend.com/insights/data-centre-construction-cost-index-2026-27/",
      "published": "2026-10-22",
      "accessed": "2026-11-16",
      "tier": "B"
    },
    {
      "title": "Boom da IA e restrições energéticas na Europa colocam Portugal entre os mercados mais competitivos (AI boom and energy constraints in Europe put Portugal among the most competitive markets)",
      "publisher": "JLL",
      "url": "https://www.jll.com/pt-pt/newsroom/boom-da-ia-e-restricoes-energeticas-na-europa-colocam",
      "published": "2026-09-29",
      "accessed": "2026-11-16",
      "tier": "B"
    },
    {
      "title": "Job vacancy statistics",
      "publisher": "Eurostat",
      "url": "https://ec.europa.eu/eurostat/statistics-explained/index.php?title=Job_vacancy_statistics",
      "published": "2026-09",
      "accessed": "2026-11-16",
      "tier": "A"
    }
  ],
  "related": [
    "https://globaldatacentertalent.com/articles/nordics-talent",
    "https://globaldatacentertalent.com/articles/germany-frankfurt-talent",
    "https://globaldatacentertalent.com/articles/grid-connection-manager",
    "https://globaldatacentertalent.com/articles/neocloud-hiring"
  ],
  "bodyMarkdown": "Spain and Portugal had about 450 MW IT of operational data centre capacity in September 2026, up 65 MW IT in six months ([Colliers, Oct 2026](https://www.colliers.com/es-es/research/data-center-snapshot-iberian-region-april-2026-sept-2026)). Colliers puts the Iberian pipeline above 10 GW ([Colliers, Oct 2026](https://www.colliers.com/es-es/research/data-center-snapshot-iberian-region-april-2026-sept-2026)). CBRE counts 4.5 GW of IT capacity as deliverable over the medium term ([Invest in Spain, Jul 2026](https://www.investinspain.org/en/news/2026/cbre)). For hiring teams, the useful question for any data centre (data center in US usage) project is which will get power first and who will build, test and run them.\n\n## How big is the data centre market in Spain and Portugal?\n\nMadrid and Barcelona led the growth. Madrid rose from 175 MW IT to 212 MW IT, and Barcelona from 42 MW IT to 63 MW IT ([Colliers, Oct 2026](https://www.colliers.com/es-es/research/data-center-snapshot-iberian-region-april-2026-sept-2026)). Cushman & Wakefield ranks Madrid as the fifth primary market in EMEA and reports roughly 9% year-on-year growth in Spain's operational capacity ([Cushman & Wakefield, Jun 2026](https://www.cushmanwakefield.com/en/spain/news/2026/06/madrid-ranks-among-the-top-five-data-center-markets-in-emea)).\n\nNew supply is not yet keeping up with demand. Operational colocation availability is 19% in Madrid and 14% in Barcelona, and 9% in Madrid and nil in Barcelona for hyperscale and neocloud tenants ([Colliers, Oct 2026](https://www.colliers.com/es-es/research/data-center-snapshot-iberian-region-april-2026-sept-2026)).\n\n## Where are data centres in Spain being built?\n\nFour places carry most of the Spanish pipeline: Madrid, Barcelona, Aragón and newer locations such as Derio, Paterna and Cantabria. Cushman & Wakefield names Madrid, Barcelona and Zaragoza among the markets drawing growing interest ([Cushman & Wakefield, Sep 2026](https://www.cushmanwakefield.com/en/netherlands/news/2026/09/europese-datacenter-capaciteit-passeert-de-12gw)).\n\n| Market | Operational, Mar to Sep 2026 (MW IT) | Planned pipeline (MW IT) | What changed |\n|---|---|---|---|\n| Madrid | 175 to 212 | not stated | Up 21% in six months ([Colliers, Oct 2026](https://www.colliers.com/es-es/research/data-center-snapshot-iberian-region-april-2026-sept-2026)) |\n| Barcelona | 42 to 63 | not stated | Up 50% in six months ([Colliers, Oct 2026](https://www.colliers.com/es-es/research/data-center-snapshot-iberian-region-april-2026-sept-2026)) |\n| Aragón | 108 to 108 | 3,764 | No new live capacity; pipeline up from 3,461 ([Colliers, Oct 2026](https://www.colliers.com/es-es/research/data-center-snapshot-iberian-region-april-2026-sept-2026)) |\n| Other Spanish locations | about 35 to 42 | 5,687 | New supply at Derio, Paterna and Cantabria; many projects at an early stage ([Colliers, Oct 2026](https://www.colliers.com/es-es/research/data-center-snapshot-iberian-region-april-2026-sept-2026)) |\n| Lisbon | 25 to 25 | 1,389 | Stable ([Colliers, Oct 2026](https://www.colliers.com/es-es/research/data-center-snapshot-iberian-region-april-2026-sept-2026)) |\n\nFigures are Colliers' latest. Its October summary gives no pipeline for Madrid or Barcelona. Colliers measures capacity as net tradable IT power, so other trackers' figures will differ. Pipelines include announced projects, and not every announced megawatt will be built or energised on schedule.\n\n## How is Aragón's hyperscale pipeline growing?\n\nAragón's planned pipeline rose from 2,790 MW IT in October 2025 to 3,461 MW IT in March 2026 ([Colliers, Apr 2026](https://go.colliers.com/rs/427-KXE-423/images/Colliers_DC_Snapshot_Oct25_Mar26_.pdf)). By September 2026 it had reached 3,764 MW IT, while live capacity stayed at 108 MW IT ([Colliers, Oct 2026](https://www.colliers.com/es-es/research/data-center-snapshot-iberian-region-april-2026-sept-2026)). In March 2026 AWS announced 33.7 billion euros of investment in Spain ([Spanish government, Mar 2026](https://digital.gob.es/comunicacion/notas-prensa/mtdfp/2026/03/el-gobierno-celebra-la-apuesta-de-amazon-por-espana-con-una-inve)). The government said Amazon would be the first technology company to plan data centres in Teruel, alongside new sites in Huesca and Zaragoza ([Spanish government, Mar 2026](https://digital.gob.es/comunicacion/notas-prensa/mtdfp/2026/03/el-gobierno-celebra-la-apuesta-de-amazon-por-espana-con-una-inve)).\n\nDelivery is the open question. In March, Colliers said the pipeline depended on grid reinforcements and the allocation of about 3,500 MW of electrical capacity ([Colliers, Apr 2026](https://go.colliers.com/rs/427-KXE-423/images/Colliers_DC_Snapshot_Oct25_Mar26_.pdf)). It also named local talent as an emerging challenge.\n\nEach campus waits on its own approval and grid allocation, so build and commissioning crews will likely move between sites in one province.\n\n## What is changing in Portugal?\n\nLisbon has 25 MW IT operational and 1,389 MW IT planned ([Colliers, Oct 2026](https://www.colliers.com/es-es/research/data-center-snapshot-iberian-region-april-2026-sept-2026)). Merlin Edged's Vila Franca de Xira campus will start with 180 MW of IT capacity and could scale to 300 MW ([JLL, Sep 2026](https://www.jll.com/pt-pt/newsroom/boom-da-ia-e-restricoes-energeticas-na-europa-colocam)). JLL places it within 1,300 MW planned for the Lisbon region ([JLL, Sep 2026](https://www.jll.com/pt-pt/newsroom/boom-da-ia-e-restricoes-energeticas-na-europa-colocam)).\n\nAt Sines, Start Campus targets 1,200 MW, and its first building, SIN01, operates at 37.5 MW of IT load ([JLL, Sep 2026](https://www.jll.com/pt-pt/newsroom/boom-da-ia-e-restricoes-energeticas-na-europa-colocam)). In January 2026 Start Campus said its second building, SIN02, would begin construction in mid-February and finish in 2027, adding 180 MW of IT load ([RTP, Jan 2026](https://www.rtp.pt/noticias/economia/start-campus-avanca-em-fevereiro-com-segundo-edificio-do-centro-de-dados-de-sines_n1709826)).\n\nGrid access has tightened. In February 2026 Portugal recognised its whole mainland network territory as a single high-demand zone ([Diário da República, Feb 2026](https://diariodarepublica.pt/dr/detalhe/despacho/1135-2026-1031758691)). JLL describes a move from first-come, first-served allocation towards financial guarantees, priority for strategic projects and capacity released in stages as projects advance ([JLL, Sep 2026](https://www.jll.com/pt-pt/newsroom/boom-da-ia-e-restricoes-energeticas-na-europa-colocam)).\n\n## How does grid access shape Spanish projects?\n\nRed Eléctrica's October 2026 map shows 18.52 GW of transmission access granted in Spain, of which 11.05 GW is not yet in service ([Red Eléctrica, Oct 2026](https://www.ree.es/es/sala-de-prensa/actualidad/nota-de-prensa/2026/10/red-electrica-publica-el-mapa-de-capacidades-de-demanda-tipo-consumo)). Data centres hold the largest share, with 6,329 MW granted, or 34.2% of the total, and none of it is yet in service ([Red Eléctrica, Oct 2026](https://www.ree.es/es/sala-de-prensa/actualidad/nota-de-prensa/2026/10/red-electrica-publica-el-mapa-de-capacidades-de-demanda-tipo-consumo)). Firm demand capacity can still be granted at more than 35% of transmission nodes ([Red Eléctrica, Oct 2026](https://www.ree.es/es/sala-de-prensa/actualidad/nota-de-prensa/2026/10/red-electrica-publica-el-mapa-de-capacidades-de-demanda-tipo-consumo)). The figures cover the transmission network only, not distribution.\n\nGranted access is not built capacity, so connection dates are likely to show when a site needs its team better than permits do.\n\nPermits granted already exceed expected demand. The ministry says it has granted grid access rights above 12 GW to data centres since 2021 ([MITECO, Aug 2026](https://www.miteco.gob.es/es/prensa/ultimas-noticias/2026/agosto/-el-gobierno-plantea-impulsar-los-centros-de-datos-sostenibles--.html)). Its AI strategy implies 3.5 to 4 GW of demand for 2030 ([MITECO, Aug 2026](https://www.miteco.gob.es/es/prensa/ultimas-noticias/2026/agosto/-el-gobierno-plantea-impulsar-los-centros-de-datos-sostenibles--.html)).\n\nRules are still moving. A draft Royal Decree of 27 August 2026 would require data centres above 1 MW to back 80% of their consumption with new hourly-matched renewable generation ([MITECO, Aug 2026](https://www.miteco.gob.es/es/prensa/ultimas-noticias/2026/agosto/-el-gobierno-plantea-impulsar-los-centros-de-datos-sostenibles--.html)). Projects already in the permitting queue would have six months to comply or give up their access rights without losing their guarantees ([MITECO, Aug 2026](https://www.miteco.gob.es/es/prensa/ultimas-noticias/2026/agosto/-el-gobierno-plantea-impulsar-los-centros-de-datos-sostenibles--.html)). In November, law firm Ashurst reported a later draft that would raise the threshold to 10 MW, and it was not yet approved ([Ashurst, Nov 2026](https://www.ashurstperkinscoie.com/es-es/insights/data-centres-what-has-changed-in-the-draft-royal-decree/)).\n\n## What does this mean for hiring teams?\n\nSkilled labour is the shared constraint. In Turner & Townsend's 2026–27 survey, 81% of respondents say skilled labour in their region is constrained, with mechanical, electrical and plumbing trades the most sought-after ([Turner & Townsend, Oct 2026](https://www.turnerandtownsend.com/insights/data-centre-construction-cost-index-2026-27/)).\n\nSpain's overall job vacancy rate was 0.9% in Q2 2026, against 2.0% for the EU ([Eurostat, Sep 2026](https://ec.europa.eu/eurostat/statistics-explained/index.php?title=Job_vacancy_statistics)). A low national rate does not mean data centre specialists are easy to find, especially for rural campuses. In Portugal, JLL frames the task as turning growth into qualified jobs ([JLL, Sep 2026](https://www.jll.com/pt-pt/newsroom/boom-da-ia-e-restricoes-energeticas-na-europa-colocam)).\n\nMost of the new capacity sits outside the established metro clusters, in Aragón, Sines and southern Madrid. Senior electrical, commissioning and operations leads will often have to relocate or rotate in while a local team is trained. With little space available in Madrid and Barcelona, operators are likely to press to bring halls into service on time, which raises the cost of a late senior hire.\n\nChecklist for staffing a data centre site in Spain or Portugal:\n\n1. Confirm the grid access status and expected energisation date with the transmission or distribution operator before opening senior searches.\n2. In Spain, ask whether the project already holds access and connection permits, since the draft decree would apply new requirements to projects still in the permitting queue.\n3. In Portugal, check whether the site already holds reserved capacity or still depends on an allocation round.\n4. Map neighbouring projects in the same province and their dates, since they compete for the same electrical and mechanical supervisors.\n5. Map each hire to its phase: enabling works, construction, commissioning or operations.\n6. Decide which senior roles must live near the site and which can travel from Madrid, Barcelona or Lisbon.\n7. Bring the commissioning lead in early enough to shape the commissioning plan, and hire the future site manager before handover.\n8. Plan a local training route for the permanent operations team, with Spanish or Portuguese as the working language on site.\n\nFor headcount by phase, see [how many people a data centre needs to build and run](/articles/how-many-people-does-a-data-center-need). For the grid-connection role behind these power queues, see [the grid connection manager](/articles/grid-connection-manager). For a comparable market where power also sets the pace, see [data centres in Norway and the Nordics](/articles/nordics-talent).\n\nHiring in Iberia? Workfully is an AI-native recruiting partner built around your hiring needs. Senior specialist recruiters deliver the hires your business needs without scaling your recruiting team. Your team interviews and decides ([Workfully for data centres](https://workfully.com/data-centres))."
}